BR1 Surge Towers Slope Stabilization
BR1 Surge Towers Slope Stabilization
| Project summary | |
|---|---|
| Project | BR1 Surge Towers Slope Stabilization | 
| Location | Shalalth, BC | 
| Client Name | Tsal’alh Development LP (TDLP) / BC Hydro | 
| Start Date – End Date | June 2021 to June 2022 | 
| Contract Value | $681,924 | 
Norpac completed the BR1 Surge Towers Slope Stabilization Project for BC Hydro in partnership with the Tsal’alh Development LP (TDLP). The scope of work included the following:
- 314 linear metres of foundation anchors
- 228 linear metres of shotcrete anchors
- 108 weep pipes
- 24 linear metres of rock anchors
- 1040 m2 of fibre-reinforced dry mix shotcrete
The site presented multiple challenges, including a wide range of temperature and weather conditions and remote location. A combination of rope access techniques and telehandler with man basket were used to access the rock slope.