Duncan Dam Fish Weir Slope Stabilization
Duncan Dam Fish Weir Slope Stabilization
Project summary | |
---|---|
Project | Duncan Dam Fish Weir Slope Stabilization |
Location | 43 km north of Kaslo, BC |
Client Name | IDL Projects / BC Hydro |
Start Date – End Date | April 2023 to June 2024 |
Contract Value | $428,356 |
Norpac was a subcontractor to IDL Projects for a slope stabilization program at the Duncan Dam. The scope of work included the following:
- Rock scaling
- 21 rock dowels
- 15.6 linear metres of rock anchors
- 47 concrete anchors
- Approximately 560 m2 of rockfall drape mesh (installed per MoTI specifications)
The site presented multiple challenges, including difficult-to-access terrain, rockfall hazards, environmental risks with the site being located adjacent to a sensitive water course, and variable ground conditions.