BR1 Debris Removal and Slope Stabilization

BR1 Debris Removal and Slope Stabilization

Project summary
ProjectBR1 Debris Removal and Slope Stabilization
LocationShalalth, BC
Client NameTsal’alh Development LP (TDLP) / BC Hydro
Start Date – End DateApil 2022 to December 2024
Contract Value$36.4M

The BR1 Debris Removal and Slope Stabilization Project was located on the penstock slopes for the Bridge River 1 Generating Station in Shalalth, BC. This was a design-build project, and the scope of work included the following:

  • Design of all aspects of the project
  • Design, installation and utilization of an innovative flume system to move the debris down 360 m on a 45° to 60° slope into steel Baker holding tanks below
  • Removal of almost 5,000 m3 of rock and organic debris from the penstock trenches
  • Vegetation removal
  • Installation of temporary rockfall slope mesh
  • 2,745 shotcrete anchors – total of 4,118 linear metres of #7 (22 mm diameter) threadbar
  • 22 rock bolts – total of 117 m linear metres of #7 (22 mm diameter) threadbar
  • 10 linear metres of borehole rock drains
  • Over 1,500 m3 of fibre-reinforced dry-mix shotcrete on rock slopes
  • 188 m3 of non-fibre-reinforced dry-mix shotcrete on soil nail walls and debris deflection walls
  • 259 linear metres of debris deflection walls
  • 679 soil nails – total of 3,465 linear metres of 32 mm diameter hollow-bar
  • 1,962 weep holes
  • 245 m3 of lumber debris removal
  • 53 tonnes of concrete debris removal
  • 17 tonnes of steel debris removal
  • 1,495 tonnes of 100/250 kg riprap placement
  • Spoil pile management and reclamation

The site presented multiple challenges, including the steep slope and difficult-to-access terrain, rockfall hazards, wide range of temperature and weather conditions, remote location and consistently safe use of a helicopter long-line for transport of materials and equipment to the slope.